RP Grid Can Accommodate 500 MW of Additional Wind


January 12, 2016

Share to:

Wind Energy Developers Association of the Philippines (WEDAP) members’ data showing average hourly wind energy production during the Amihan Season from October to March. Daily energy production peaks from 11 AM to 2 PM and 6 PM to 9 PM. These two peaks coincide with the highest daily demands for power. (WEDAP)
 
Adding 500 MW of wind power to the national grid will have no negative impacts on Philippine grid operations, reveals a 2013 World Bank and Australia AusAid report on the Grid Impact of Variable Renewable Energy (VRE) for the Philippines. “Despite wind’s variable nature, 500 MW can easily be integrated without the risk of blackouts or interruptions,” explains WWF-Philippines Climate Change Unit Head Atty. Gia Ibay.
 
“A country’s national grid should have a power reserve capacity equal to or larger than its biggest power plant. This reserve prevents blackouts, even if the grid’s biggest plant shuts down.” The 500 MW of wind provided by new wind farms in Ilocos, Rizal and Panay, is smaller than the grid’s reserve requirements, so even with their variable nature, they will not affect the grid negatively.

There will also be no grid constraint problems regarding the time of day that wind farms feed energy into the system because wind production peaks from 11 AM to 2 PM and 6 PM to 9 PM, the hours with the highest daily peak demands. This means that all generated energy will be consumed. This dispels fears of creating ‘over-contracted’ energy which goes to waste.
About 70% of Philippine electricity is currently generated from fossil-fuels, 90% of which are imported at varying prices. Humanity’s continued reliance on fossil-fuels for the transportation and energy-generation industries is the primary cause of climate change, the impacts of which are becoming more destructive yearly.
 
Climate solutions-provider World Wide Fund for Nature (WWF) is spearheading the Seize the Wind campaign to increase the Feed-in Tariff (FiT) allocation for wind energy from 200 MW to 500 MW before the end of summer. Wind produces free, clean power throughout the year with the highest production during November to April’s Amihan season.
The Seize the Wind campaign fully supports the construction of new wind farms to augment the national power supply and overcome the country’s power deficit.
About 400 MW of wind power shall be added to the national grid by April 2015.
 
For more information, please contact:
 
Atty. Angela Consuelo Ibay
Climate Change and Energy Programme Head
WWF-Philippines
gibay@wwf.org.ph
 
 
Mr. Gregg Yan
Communications and Media Manager
WWF-Philippines
gyan@wwf.org.ph
 
 
Mr. Christopher Ng
Renewable Energy Coordinator, Climate Change and Energy Programme
WWF-Philippines
cng@wwf.org.ph

Share to:

GET IN TOUCH WITH US

We would love to hear from you! Feel free to contact us through any of the details listed below.

WWF–Philippines Headquarters

4th Floor JBD Plaza #65 Mindanao Ave.
Barangay Bagong Pag-asa,
Quezon City 1105 Philippines

Tel: +632 920 7923 / 7926 / 7931
Fax: +632 426 3927
Email: teampanda@wwf.org.ph

NEWSLETTER SIGN UP

×

CONNECT WITH US